ITEM DESCRIPTION QUANTITY UNIT   EXTENSION
         
General conditions        
General conditions 1  $              4,000.00 ea.  $                            4,000.00
Trucking and material handling 1  $                 300.00 ea.  $                               300.00
Supervision 1  $              3,000.00 ea.  $                            3,000.00
Equipment rentals 1  $                 300.00 ea.  $                               300.00
Dumpster 1  $              1,500.00 ea.  $                            1,500.00
Barricades and protection 1  $                 300.00 ea.  $                               300.00
Nails, fasteners, etc. 1  $                 100.00 ea.  $                               100.00
Miscellaneous items 1  $                 500.00 ea.  $                               500.00
Demolition        
Selective demolition 6  $                 200.00 man day  $                            1,200.00
Sitework        
Site Layout 1  $                 150.00 ea.  $                               150.00
Rock excavation 35  $                 100.00 CY  $                            3,500.00
Backfill 40  $                   20.00 CY  $                               800.00
Fine grading 1  $                 200.00 LS  $                               200.00
Topsoil and seed 1  $                 500.00 LS  $                               500.00
New Vee-drainage swale on hill above addition 1  $              1,500.00 LS  $                            1,500.00
New asphalt dished gutter behind addition 40  $                     8.00 LF  $                               320.00
New front wood stairs with 2 handrails 1  $                 600.00 ea.  $                               600.00
Concrete        
Footings 5  $                 150.00 SY  $                               750.00
Foundation walls 16  $                 160.00 SY  $                            2,560.00
Floor slab 230  $                     5.00 SF  $                            1,150.00
Basement steps 12  $                   60.00 riser  $                               720.00
Pad at door 1  $                 200.00 ea.  $                               200.00
Pad at front steps 1  $                   75.00 ea.  $                                 75.00
Dumpster pad 80  $                     8.00 SF  $                               640.00
Sonotube footings for exterior steel stair 1  $                 100.00 LS  $                               100.00
Framing, Drywall, Doors & Frames, Windows, Kitchen, Finish Carpentry, Misc. Metals, Finish Materials        
Interior walls 45  $                   30.00 LF  $                            1,350.00
Addition walls 206  $                   30.00 LF  $                            6,180.00
Second floor joists and sheathing 432  $                     2.25 SF  $                               972.00
Roof framing rafters, ceiling joists and sheathing 1  $              3,500.00 LS  $                            3,500.00
Shingles and ice guard underlayment 1  $              2,000.00 LS  $                            2,000.00
Misc. fascia, ridge and collar ties 1  $                 300.00 LS  $                               300.00
Add 2 columns in basement 2  $                   50.00 ea.  $                               100.00
Infill floor at old basement stair 1  $                 150.00 ea.  $                               150.00
Misc. framing, header in dining room, patch & paint 1  $                 700.00 LS  $                               700.00
New  porch subflooring on sleepers 160  $                     2.00 SF  $                               320.00
Drywall taped and painted 1200  $                     1.50 SF  $                            1,800.00
Doors and frames 17  $                 500.00 ea.  $                            8,500.00
Paint doors and trim 17  $                   50.00 ea.  $                               850.00
Windows 13  $                 400.00 ea.  $                            5,200.00
Paint window interior trim 13  $                   30.00 ea.  $                               390.00
Kitchen cabinets and counter (HUD spec) 20  $                 300.00 LF  $                            6,000.00
Range and hood 1  $              4,500.00 LS  $                            4,500.00
Dishwasher 1  $                 600.00 ea.  $                               600.00
Closet rods and shelves 6  $                   50.00 ea.  $                               300.00
Steel exit stair 16  $                 175.00 riser  $                            2,800.00
Floor finishes allowance 1400  $                     2.50 SF  $                            3,500.00
Baseboard moldings 1  $                 800.00 LS  $                               800.00
Bathroom finishes allowance 1  $              2,000.00 ea.  $                            2,000.00
Insulation foundation, walls, ceiling 1  $                 600.00 LS  $                               600.00
Bathroom accessories 1  $                 100.00 ea.  $                               100.00
Siding, fascia and soffit
Siding (new addition only) 1  $              7,000.00 LS  $                            7,000.00
Trim and soffit 1  $                 350.00 LS  $                               350.00
Plumbing 1  $              5,000.00 LS  $                            5,000.00
Heating and ventilation 1  $              5,000.00 LS  $                            5,000.00
Electrical 1  $              6,300.00 LS  $                            6,300.00
Subtotal proposed construction work        $                     102,127.00
Contractor overhead and profit at 25%        $                       25,531.75
Subtotal        $                     127,658.75
Contingency at 15%        $                       19,148.81
Total proposed construction work        $                     146,807.56